The City and County of Honolulu’s Phase 1C expansion at the Honouliuli WWTP in ʻEwa Beach, led by Hensel Phelps, adds headworks screening and grit removal, high-rate biological contactor treatment, and solids, biogas, and combined heat-and-power upgrades.

Soldier Piles Lagging
Pacific Foundation Scope

Scope of Work

For Hensel Phelps, Pacific Foundation has installed 34 W18×86 soldier piles, 4,420 square feet of wood lagging, tieback anchors, and handrail for excavation support using a Bauer BG33 and Klemm 806. The package also includes phased probe-and-grout work across multiple construction windows.

Field Execution

Methods and Site Conditions

Methods

Method Soldier Piles Lagging Listed project method.