Bridges & Transportation
Meacham Creek Bridge
Pendleton, OR
ODOT replaced the Old Emigrant Springs Frontage Road bridge over Meacham Creek and Union Pacific Railroad in Umatilla County. Oregon State Bridge Construction delivered the project, which was completed in December 2025.
Drilled Shafts
Reinforcement Cage Installation
Concrete Placement
Pacific Foundation Scope
Scope of Work
Pacific Foundation advanced casing and drilled the replacement bridge foundation holes through native soils, removing spoils as excavation progressed before setting reinforcement cages and placing concrete.
Field Execution
Methods and Site Conditions
Methods
Service
Drilled Shafts
Large-diameter reinforced-concrete foundations for heavy structural loads and deep support.
Method
Reinforcement Cage Installation
Method
Concrete Placement
Site Constraints
Sloped bridge work area
Related Capabilities
Services and equipment
Next Step
Request Scope Review
Send Us Your Plans
Send the drawings, specifications, geotechnical report, pile or shaft schedule, and site constraints. Pacific Foundation can review the foundation scope and next steps.