UO Friendly Hall
General Civil

UO Friendly Hall

Eugene, OR

The University of Oregon is fully renovating Friendly Hall, the 1893 unreinforced-masonry building on the Old Campus Quad, to address seismic and life-safety deficiencies, improve accessibility, and consolidate Global Studies and Languages programs.

Lagging Micropiles Soldier Piles Tiebacks
Pacific Foundation Scope

Scope of Work

Working for Bremik, Pacific Foundation’s below-grade package combined 10 conventional soldier piles with lagging, 12 soil nails, tiebacks, and two micropiles. A compact Klemm drill rig and hollow-bar elements supported the mixed shoring and foundation work.

Field Execution

Methods and Site Conditions

Methods

Service Micropiles Drilled and grouted foundation elements for constrained access, low overhead, existing structures, bridge retrofit, underpinning, and difficult ground.
Method Soldier Piles Listed project method.
Method Lagging Listed project method.
Method Tiebacks Listed project method.